All information, specifications, rendering, visual representations and plans are current at the time of publication and are subject to change as may be required by us and/or the competent authorities, and shall not form part of any offer or contract nor constitute any warranty by us and shall not be regarded as statements or representations of fact.

DEVELOPMENT PROGRESS

November Week 5, 2021
Preparation for Strut Beam
November Week 5, 2021
Drilling and Concrete Casting for Bored Pile
November Week 5, 2021
Rebar Yard
November Week 5, 2021
Anti-mosquito oiling at office and site
November Week 5, 2021
Safety induction before commencement of works
November Week 5, 2021
Drilling diaphragm wall concrete
November Week 5, 2021
Drilling diaphragm wall concrete
November Week 5, 2021
Fabrication of rebar cage for bored pile
November Week 5, 2021
Installation of rebar cage for bored pile
November Week 5, 2021
Fabrication of rebar cage for bored pile
November Week 5, 2021
Drilling of bored pile
November Week 5, 2021
Excavate and compaction of soil
November Week 5, 2021
Excavate and compaction of soil
November Week 5, 2021
Excavation of soil
November Week 5, 2021
Installation of rebar cage for bored pile
November Week 5, 2021
Embedding rebar to diaphragm wall
November Week 5, 2021
Concrete casting for bored pile
November Week 5, 2021
Drilling of bored pile
October Week 4, 2021
Soil Excavation
October Week 4, 2021
Drilling of Bored Pile
October Week 4, 2021
Rebar Yard
October Week 4, 2021
Safety induction before commencement of works
October Week 4, 2021
Hacking of temporary guide wall and diaphragm wall concrete
October Week 4, 2021
Installation of safety barricade
October Week 4, 2021
Ongoing soil excavation
October Week 4, 2021
Fabrication of rebar cage for bored pile
October Week 4, 2021
Installation of rebar for boundary beam
October Week 4, 2021
Ongoing soil excavation
October Week 4, 2021
Ongoing drilling of bored pile
October Week 4, 2021
Fabrication of rebar cage for bored pile
October Week 4, 2021
Drilling of bored pile
October Week 4, 2021
Hacking of diaphragm wall concrete
October Week 4, 2021
Installation of boundary beam formwork
October Week 4, 2021
Ongoing soil excavation 3
October Week 4, 2021
Hacking of diaphragm wall concrete
October Week 4, 2021
Concrete casting for bored pile
October Week 4, 2021
Ongoing soil excavation 4
February Week 1, 2021
Site Overview - Bored Pile Rebar
February Week 1, 2021
Installation of Rebar Cage & Steel Plate of Bored Pile
February Week 1, 2021
Site Overview - Rebar Fabrication Yard & Heavy Machinery Parking
February Week 1, 2021
Installation of Rebar Cage & Steel Plate of Bored Pile
February Week 1, 2021
Installation of Rebar Cage & Steel Plate of Bored Pile
February Week 1, 2021
Installation of Rebar Cage & Steel Plate of Bored Pile
February Week 1, 2021
Ongoing Drilling of Bored Pile
February Week 1, 2021
Concrete Casting for Bored Pile
February Week 1, 2021
Fabrication of Rebar Cage for Bored Pile
February Week 1, 2021
Ongoing Drilling & Concrete Casting for Bored Pile
February Week 2, 2021
Site overview - Rebar Fabrication Yard & Heavy Machinery Parking Place
February Week 2, 2021
Site overview - Rebar Fabrication Yard
February Week 2, 2021
Installation of Rebar Cage & Steel Plate of Bored Pile
February Week 2, 2021
Ongoing Drilling For Bored Pile
February Week 2, 2021
Rock Filling for Bored Pile
February Week 2, 2021
Ongoing Drilling for Bored Pile
February Week 2, 2021
Concrete Casting for Bored Pile
February Week 2, 2021
Rock Filling for Bored Pile Hole
January Week 4, 2021
Site Overview
January Week 4, 2021
Rebar Yard
January Week 4, 2021
Rebar Yard & Heavy Machinery Parking Space
January Week 4, 2021
Safety Induction Before Commencement of Works
January Week 4, 2021
Fabrication of Rebar Cage
January Week 4, 2021
Ongoing Drilling of Bored Pile
January Week 4, 2021
Installation of Rebar Cage for Bored Pile
January Week 4, 2021
Fabrication of Rebar Cage for Bored Pile
January Week 4, 2021
Ongoing Drilling for Bored Pile
January Week 4, 2021
Drilling for Bored Pile
January Week 4, 2021
Sonic Testing for Diaphragm Wall
January Week 4, 2021
Concrete Casting for Bored Pile
Previous
Next

For enquiries, please schedule an appointment with us.

©2021 Leedon Group. All rights reserved.

All information, specifications, rendering, visual representations and plans are current at the time of publication and are subject to change as may be required by us and/or the competent authorities, and shall not form part of any offer or contract nor constitute any warranty by us and shall not be regarded as statements or representations of fact.